Champion delivered nearly one-half million square feet of accommodations in six months. The Company’s off-site construction efficiently remedied delays and challenges created by increased base security.

PROJECT SCOPE
Champion modular building process was selected to provide:
  • Modularity project for Army Corp of Engineers
  • Genesis constructed 63 barrack buildings
  • Buildings contained 504 apartments accommodating 15,012 soldiers
  • Champion dedicated one manufacturing facility to meet aggressive delivery schedule
  • All construction in accordance with commercial modular code
CHALLENGE
Build quickly and efficiently on army base where restrictive increased security resulted in construction and building challenges.

SOLUTION
  • Built 63 barrack buildings of 7,435 square feet each


CLIENT